Boyle Construction

Boyle Construction

Project Profile

Cetronia Ambulance Corps New Headquarters

Allentown, Pennsylvania

Client
Cetronia Ambulance Corps
Contact Name
Mr. Larry Wiersch, CEO
Architect
Spillman Farmer Architects
Keystone Consulting Engineers
Snyder Hoffman Associates
Barry Isett Associates
Services
Agency Construction Management
Final CM Budget
$8,862,000
Base Bids
$7,865,000
Total Change Orders
$965,805*
Percentage Change Orders
12%
Final Costs incl. C.O.s
$8,492,243
*Change order due to rock and sinkhole remediation.
CM Services Start Date
April 2013
Construction Start Date
January 2014
Project Completion Date
July 2014

Project Description

The new Cetronia Ambulance Corps Headquarters is a 68,000 SF facility for the joint operations of Cetronia Ambulance Corps and Lehigh County Emergency Management Services. The facility provides an administration and dispatch headquarters for the Cetronia Ambulance Corps’ regional emergency transport service, and it features a 35,000 SF garage and maintenance facility for Cetronia’s ambulance fleet. The Lehigh County Forensics Medicolegal Center is also a tenant of this state-of-the-art building.

Boyle’s services included construction management, value engineering and design team coordination.