Freemansburg Borough Police Station Addition, Phases 1, 2 and 3

Freemansburg, Pennsylvania

Client
Freemansburg Borough
Contact Name
Ms. Judith Danko, Borough Manager
Consultants
MKSD Architects
T&M Associates
Services
Agency Construction Management
Contracts
Public procurement, multi prime, 9 - Prime contractors for two phases
Final CM Budget
$958,400
Base Bids
$914,168
Total Change Orders
$24,904
Percentage Change Orders
2.7%
Final Costs incl. C.O.s
$939,072
CM Services Start Date
December 2011 / May 2013
Construction Start Date
February 2012 / July 2013
Project Completion Date
July 2012 / October 2013

Project Description

With Freemansburg Borough experiencing a 39% growth rate from 2000 to 2010 (the largest growth for a Lehigh Valley Borough), the Borough expanded its Police Station with an addition to its municipal building. The 3,000 SF expansion improved the existing Borough offices and houses the Borough’s Police Department.

The addition provides modern facilities such as new offices, a file room, a data room, two holding cells, an evidence room and a shower facility for prisoners.

Local casino impact fees funded a majority of the project costs.