Project Profile

Lower Gwynedd Township Municipal Building

Spring House, Pennsylvania

Client
Lower Gwynedd Township
Contact Name
Mr. Larry Comunale, Township Manager
Consultants
Joseph A. Zadlo Architects
Wachter & Associates
CKS Engineers, Inc.
Services
Agency Construction Management
Contracts
Public procurement, multi prime, 5 - Prime contractors
Final CM Budget
$1,250,000
Base Bids
$1,064,830
Total Change Orders
$184,199*
Percentage Change Orders
17.3%
Final Costs incl. C.O.s
$1,249,028
*$140,000 of the total change orders were Owner initiated, for adding additional finish work to portions of the building that were previously to have no work performed. Furniture systems were also added to this contract.
CM Services Start Date
June 2005
Construction Start Date
October 2005
Project Completion Date
April 2006

Project Description

Lower Gwynedd Township was running out of space in its existing municipal building, which is utilized by both the Police Depart-ment and Administrative staff. Two separate additions were designed to expand both departments. Along with the addition of 2,600 SF of new space and 4,000 SF of renovated space, the entire 15,000 building received new interior finishes.

The work was completed in phases to allow the building to remain fully functional throughout the renovation process. The structure and addition finishes match the original building, including stone veneer, blue stone sill and EFIS finishes.