Project Profile

City of Easton New City Hall

Easton, Pennsylvania

Client
City of Easton
Contact Name
Mayor Sal Panto
Consultants
Spillman Farmer Architects
Services
General Construction
Winning Bid
$9,956,760
Total Change Orders
$173,395
Percentage Change Orders
1.74%
Final Costs incl. C.O.s
$10,130,155
Construction Start Date
September 2014
Project Completion Date
October 2015

Project Description

Boyle provided site work, development and general contractor services for a new 46,000 SF City Hall administrative office and meeting facility building with ground floor retail and restaurant amenities. Site work included bulk excavation, new underground utility infrastructure and tie into a newly constructed parking garage.

Amenities include LANTA transit center, two-story lobby, glass elevator shaft, floor to ceiling glass windows, exposed structural steel and skylights. An outside exterior plaza adds to the lot beautification. All recycled materials were included in accordance with the LEED certification program.