Project Profile

Lower Macungie Township Library and Community Center

Macungie, Pennsylvania

Client
Lower Macungie Township
Contact Name
Mr. Dennis Hinkel, Public Works Director
Consultant
LB&W Design Associates, Inc.
Services
Agency Construction Management
Contracts
Public procurement, multi prime, 6 - Prime contractors
Final CM Budget
$4,258,000
Base Bids
$3,848,004
Total Change Orders
$338,048*
Percentage Change Orders
8.7%
Final Costs incl. C.O.s
$4,186,052
*$293,000 of the total change orders were owner- initiated changes for additional scope for parking lots not related to this project, library equipment and road work right-of-way.
CM Services Start Date
August 1999
Construction Start Date
May 2000
Project Completion Date
January 2001

Project Description

Boyle oversaw site work, development and construction management for a new 34,000 SF community library and recreation center. Site work included complete clearing and grubbing, excavation, utilities, paving and landscaping.

The project included building a cluster of three pre-engineered buildings, with masonry veneer. and featured a gymnasium, meeting rooms and a library.