Increased access to services
LCCC hired Boyle to oversee a 60,000 SF phased renovation of the administration building that includes admissions, financial aid and the student center. All operations remained fully functional during construction, with Boyle creating a detailed moving schedule to rotate services into areas that were not under renovation. The Administration Building, originally built in 1969, now offers new offices and student support centers to better access staff and assist student needs. Upgrades were also made to all the infrastructure to improve energy efficiency.
Client: Lehigh Carbon Community College
Project: LCCC Administration Building
Location: Schnecksville, Pennsylvania
The Boyle360 Advantage
Boyle360 is an early-stage project partnership from Boyle Construction that brings collaboration, owner-side insight, and strategic planning into your project before design begins, helping you make smart decisions, control costs, and reduce risk.