Project Profile

East Side Fire Station

Allentown, Pennsylvania

Client
City of A llentown
Contact Name
Mayor Ed Pawlowski
Consultants
W2A Architects
Liberty Engineering, Inc.
Pany & Lentz Engineering Company
Services
Agency Construction Management
Contracts
Public procurement, multi prime, 4 - Prime contractors
Final CM Budget
$1,901,600
Base Bids
$1,906,293
Total Change Orders
$41,794
Percentage Change Orders
2.2%
Final Costs incl. C.O.s
$1,948,087
CM Services Start Date
March 2013
Construction Start Date
July 2013
Project Completion Date
December 2013

Project Description

The City of Allentown asked Boyle Construction to assist in managing the East Side Fire Station project to come in on the $1.9 million budget, after cost overruns jeopardized construction start. Boyle provided construction management services for the three-bay, 7,500 SF fire station.

After a few months of collaborating with designers and assisting in multiple budgets, the new bids came in on budget, enabling the project to move forward. The three-bay, two-story Fire Station has women’s quarters for the first time, as well as a better handling of water drainage during periods of high water tables. The new station houses three firefighters but can accommodate up to eight, as well as two paramedics.