Boyle Construction

Boyle Construction

Project Profile

Shiloh Baptist Church

Easton, Pennsylvania

Client
Shiloh Baptist Church
Consultant
Z Architects
Services
General Contractor
Project Date
2003

Project Description

Boyle constructed the Shiloh Baptist Church in 2003. Over the years, the firm completed many renovations to accommodate Shiloh’s needs. The original church was 37,000 SF with 1,400 seating capacity and sanctuary.

Boyle worked with the team during the preconstruction phase and developed project schedules and budgeting for multiple preliminary schemes; performed value engineering; administered the bidding process; and provided the Building Committee with complete bid tabulations for its approval. During construction, Boyle provided a full-time onsite Site Superintendent and Project Manager to oversee submittals, change orders and requests for information; conduct weekly progress meetings; review monthly invoices, submittals and change orders; and maintain the overall construction schedule.